Important PeopleCert PRINCE2 Agile Practitioner Exam Questions

CertPrep PeopleCert PRINCE2 Agile Practitioner Exam Questions
Get Full Version

PeopleCert PRINCE2 Agile Practitioner Project Management PRINCE2 Agile Practitioner Exam

Attempt the Project, Programme and Portfolio Management practice test and solve real exam-like PRINCE2 Agile Practitioner questions to prepare efficiently and increase your chances of success. Our PeopleCert PRINCE2 Agile Practitioner practice questions match the actual PRINCE2 Agile Practitioner Project Management exam format, helping you enhance confidence and improve performance. With our PRINCE2 Agile Practitioner practice exam software, you can analyze your performance, identify weak areas, and work on them effectively to boost your final Project, Programme and Portfolio Management exam score.

Vendor: PeopleCert
Exam Name: PRINCE2 Agile Practitioner Project Management
Registration Code: PRINCE2-Agile-Practitioner
Related Certification: PeopleCert Project, Programme and Portfolio Management Certification
Exam Audience: Prince 2 Agile Practitioners and Project Managers,

Total Questions

50

Last Updated

07-07-2026

Exam Duration

150 MINUTES

Upgrade to Premium

GET FULL PDF

Question: 1

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

 Exam Question 1 Exhibit 1

Website - Additional information

A new website will be built for the event. There are five work packages within this product:

1. Initial homepage:

2. Team Registration functionality:

3. Social media promoting the event and its aims.

4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.

5. Health Park:

The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.

The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.

Using the Project Scenario and Website Additional information, answer the following question:

There are several work packages being delivered during Stage 4. The Website Team Scrum Master is concerned that project-level issues may be overlooked and this might impact the Website Team during the current timebox.

Which agile way of working can be used as part of the 'controlling a stage' process to ensure that these issues are identified?

Question: 2

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

 Exam Question 2 Exhibit 1

Marketing - Additional information

The marketing campaign has two key areas to promote:

1. The event itself including the football tournament, event village and fundraising activities.

2. The LGA's long term aim to improve the fitness of children under the age of 16.

The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.

The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.

They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.

The Marketing Team is not clear on the priority to assign to the two aims for the event.

The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.

Nine releases are scheduled at the end of each of the nine week-long timeboxes.

The nine timeboxes within the marketing work stream are scheduled to include:

Using the Project Scenario and Marketing Additional information, answer the following question:

Which approach BEST outlines how to apply the 'continued business justification' principle during the initiation stage?

Question: 3

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

 Exam Question 3 Exhibit 1

Marketing - Additional information

The marketing campaign has two key areas to promote:

1. The event itself including the football tournament, event village and fundraising activities.

2. The LGA's long term aim to improve the fitness of children under the age of 16.

The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.

The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.

They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.

The Marketing Team is not clear on the priority to assign to the two aims for the event.

The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.

Nine releases are scheduled at the end of each of the nine week-long timeboxes.

The nine timeboxes within the marketing work stream are scheduled to include:

Using the Project Scenario and Marketing Additional information, answer the following question:

Many Marketing Team members were expressing frustration that some members of the team had worked only on specific products and had not helped in the delivery of others. Therefore, the Marketing Team produced a Glad! Sad! Mad! board during a recent retrospective.

Which statement explains why this approach to identifying issues is appropriate for the 'controlling a stage' process?

Question: 4

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

 Exam Question 4 Exhibit 1

Marketing - Additional information

The marketing campaign has two key areas to promote:

1. The event itself including the football tournament, event village and fundraising activities.

2. The LGA's long term aim to improve the fitness of children under the age of 16.

The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.

The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.

They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.

The Marketing Team is not clear on the priority to assign to the two aims for the event.

The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.

Nine releases are scheduled at the end of each of the nine week-long timeboxes.

The nine timeboxes within the marketing work stream are scheduled to include:

Using the Project Scenario and Marketing Additional information, answer the following question:

When contributing to the development of the communication management approach, the Marketing Team felt that the only applicable agile technique to be included in the approach was the use of daily stand-ups.

Which reason BEST explains whether this is a suitable entry for 'tools and techniques' in the communication management approach?

Question: 5

Project scenario - Get fit with football!

(Note: The companies and people within the scenario are fictional)

Introduction

A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.

Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.

This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.

Scope

The initial scope of the project includes:

The project has been set up with four work streams to deliver this work:

1. Marketing

2. Website

3. Event Village

4. Staff Training

Project Background

The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.

Timeline

An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

 Exam Question 5 Exhibit 1

Event Village - Additional information

The aim of the event village is to provide a range of services and activities for anyone attending the football tournament.

The event village will comprise a number of work packages:

1. Event village design

2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities

3. Stalls which will be sold to local businesses to raise funds for the event:

4. A car park for 200 cars.

5. Temporary facilities including changing rooms, toilets and shower facilities.

6. Dismantling of the event village and clean up.

The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.

Using the Project Scenario and Event Village Additional information, answer the following question:

There is limited space in the Event Village to accommodate all of the equipment, e.g. the trampolines, 'kidz-zone', food tent, car park and changing rooms.

It is difficult to assess whether there is sufficient space from the design drawings. One of the team has suggested physically drawing out the actual space occupied by each facility at the site.

Which statement BEST describes whether this approach is a good application of the frequent releases focus area?

Other PeopleCert Certification Exams

MSP Foundation Exam

MSP Foundation, 5th Edition

DevOps-Leader Exam

DevOps Leader v2.2 Exam

PRINCE2-Foundation Exam

PRINCE 2 Foundation (7th Edition)

ITIL-5-Foundation Exam

ITIL Foundation (Version 5)

ITIL 4 Specialist High velocity IT Exam

ITIL 4 Specialist: High-velocity IT Exam

DevOps SRE Exam

Site Reliability Engineering Foundation v1.2